The weather this week really slowed things down. Tuesday morning we had a really bad ice storm, and the rest of the week the temperature was in the 30's. However, they are working on putting in the heating and air unit.
Sunday, January 27, 2008
Friday, January 18, 2008
Drywall
Saturday, January 12, 2008
Insulation
The insulation was completed this week. The drywall was also delivered, and I believe they are supposed to start Monday on that. Still working on the bricking, but as you can see we have front steps now.
Saturday, January 5, 2008
The Roof is Done
Between the rain and cold weather, it has still been slow going. However, it was warm enough last Monday for the roof to be completed. All that is left of the bricking is what you see around the window in the front. The wiring for the electric as well as the cable and phone is also complete. Once the bricking is complete, some fill dirt will be brought and placed around the house. Next after that is starting the insulation and drywall.