Lighting

The electrician started today and will be finished in the next 1-2 days. With the way things are scheduled to go the next few weeks, I will probably have almost daily posts.
Outside the front door.



The office.

Hallway to bedrooms.

Looking into the foyer and dining room.

Dining room.

Master bedroom.

Friday, March 28, 2008

Paint and Appliances

All of the trim is up, and all the walls and trim have been painted. The red wall you see below is in the office, which has a Titans theme. This is just the base coat. More dirt has also been added in front of the house, which you can tell from the change in the slope in front of the driveway. Our appliances also got delivered today. The refrigerator is hooked up and working. The electrician and plumber will be in next week to finish hooking up the rest of the appliances and to finish the rest of the electrical and plumbing. The countertops are also going in next week. I don't know if I mentioned this in the last post or not, but we are tentatively about 4 weeks away from moving in!












Wednesday, March 19, 2008

Door and Concrete

The trim carpenter got started today. He put up moldings around most of the doors, windows, and arches. All of the interior doors are up as well. The front stoop, garage, and half the driveway are now concrete. The bottom half of the driveway will get finished as soon as it stops raining.




















Friday, March 14, 2008

Cabinets

The kitchen and master bath cabinets were installed this week. The master bath countertop is in. The countertops for the kitchen will take a little bit longer. Someone will come and measure the cabinets on Monday and it will take 2-3 weeks for them to cut the granite and get it back to install.

















The hardwood install is complete. This is looking down the hall to the bedrooms.
The garage, ready to have concrete poured.




Thursday, March 13, 2008

Flooring